PROJECT SCOPE
This project involves the design and construction (Design/Build) of a pedestrian bridge over the Florida Turnpike exit ramp (Exit #2X) for Hard Rock Stadium. The Scope of Work includes the construction of a steel bridge, Mechanically Stabilizing Earth (MSE) or retaining walls, drainage improvements, curb and gutter, ADA sidewalk and ramp reconstruction, roadway reconstruction, parking lot modification and resurfacing. A pedestrian bridge over NW 199 Street and two tunnels under Don Shula Drive, the stadium perimeter road, will also be constructed as part of the project to improve pedestrian access and enhance public safety.
FIN No. 440858-2-54-01: City of Miami Gardens Pedestrian Safety Improvements Bridge/Tunnel
This project involves the Design/Build of a pedestrian bridge over NW 199 Street and two tunnels under Don Shula Drive. The Scope of Work includes the construction of a precast tunnel, Mechanically Stabilized Earth (MSE) or retaining walls, a steel bridge, drainage improvements, roadway reconstruction, parking lot modifications, irrigation and landscaping.
FIN No. 440858-1-58-01: Turnpike Feeder Road at NW 199 Street Pedestrian Overpass
This project involves the Design/Build of a pedestrian bridge over the Florida Turnpike exit ramp (Exit #2X) for Hard Rock Stadium. The Scope of Work includes the construction of a steel bridge, Mechanically Stabilizing Earth (MSE) or retaining walls, drainage improvement, curb and gutter, ADA sidewalk and ramp reconstruction, parking lot modification and resurfacing.
FIN No. 440858-2-54-01: City of Miami Gardens Pedestrian Safety Improvements Bridge/Tunnel
This project involves the Design/Build of a pedestrian bridge over NW 199 Street and two tunnels under Don Shula Drive. The Scope of Work includes the construction of a precast tunnel, Mechanically Stabilized Earth (MSE) or retaining walls, a steel bridge, drainage improvements, roadway reconstruction, parking lot modifications, irrigation and landscaping.
FIN No. 440858-1-58-01: Turnpike Feeder Road at NW 199 Street Pedestrian Overpass
This project involves the Design/Build of a pedestrian bridge over the Florida Turnpike exit ramp (Exit #2X) for Hard Rock Stadium. The Scope of Work includes the construction of a steel bridge, Mechanically Stabilizing Earth (MSE) or retaining walls, drainage improvement, curb and gutter, ADA sidewalk and ramp reconstruction, parking lot modification and resurfacing.
PROJECT COST
$15 Million
|
PROJECT MAP
Construction activities will be performed on-site at Hard Rock Stadium, 347 Don Shula Drive, Miami Gardens, Florida 33056.
PROJECT SCHEDULE
Design activities for the project began in August 2018. Construction began in January 2019 and will continue until September 2019, with final project completion set for December 2019.
LANE CLOSURE AND DETOUR INFORMATION
PROJECT DOCUMENTS
FACT SHEETS MAPS
ALWAYS PUT SAFETY FIRST
For your safety and the safety of others, please use caution when driving around any construction zone. While driving, wearing a seat belt is the single most effective way to protect people and reduce fatalities in motor vehicle crashes. While the project partners take steps to reduce construction impacts, you might experience travel lane closures, increased dust and noise and workers and equipment moving around the work zone.